Commissioning sequence:
Check polarity of all DC cables. | |
Check cross sectional area of all DC cables. | |
Check if all cable lugs have been crimped correctly. | |
Check if all cable connections are tight (don’t exceed maximum torque). | |
Tug slightly on each battery cable to check if the connections are tight and if the cable lugs have been crimped correctly. |