6. Commissioning the Lynx Power In

In this section:

Commissioning sequence:

checkbox.svg

Check polarity of all DC cables.

checkbox.svg

Check cross sectional area of all DC cables.

checkbox.svg

Check if all cable lugs have been crimped correctly.

checkbox.svg

Check if all cable connections are tight (don’t exceed maximum torque).

checkbox.svg

Tug slightly on each battery cable to check if the connections are tight and if the cable lugs have been crimped correctly.