7. Commissioning the Lynx Shunt VE.Can
In this section:
Commissioning sequence:
Check polarity of all DC cables. | |
Check cross sectional area of all DC cables. | |
Check if all cable lugs have been crimped correctly. | |
Check if all cable connections are tight (don’t exceed maximum torque). | |
Tug slightly on each battery cable to check if the connections are tight and if the cable lugs have been crimped correctly. | |
Turn a load on and see if the battery monitor displays the correct current polarity. | |
Fully charge the battery, so that the battery monitor synchronises. |